Construction scheduling, tracking and resources like MS Project
Scheduling a project in a separate sheet means copying items and durations, and the schedule goes stale with the first change to the budget. In ERPSqlite the schedule comes from the budget itself: every chapter and item has its duration, its predecessors and its calendar, and the program computes dates, slack and the critical path with the same method as MS Project. This guide explains what it does, how to use it and what it does not do yet.

Each item's duration
If you type nothing, the duration is the quantity divided by the performance (what the crew does in a day) or, when the item has no performance of its own, what its labor and equipment hours give. You can also type it in “Duration”:
- 5 means five working days of the calendar.
- 2 sem, 16h or 1 mes are converted to days with the calendar's working day and week.
- 3dt means three consecutive days, Saturdays and holidays included: for curing and drying that do not stop.
- An item marked as “Milestone” takes no time and shows as a diamond, for example the handover.
Links between items
Predecessors are written with the chapter or item code, as in the MS Project column, separated by semicolons. 3 is finish-to-start, 01.02SS+2d starts two days after 01.02 starts, 4FF finishes when 4 finishes and 5FS-25% starts when a quarter of 5 is left. They can also be drawn on the Gantt by dragging the dot at the end of a bar onto another, and removed with a right click.
A link to a chapter applies to everything inside it. Items without predecessors can be chained, one after another in tree order, as before. If a link would close a loop, the program rejects it and says so.

Working calendars
Three come built in: “Standard” (Monday to Friday, 8 to 12 and 13 to 17), “Night shift” and “24 hours”. You can copy them or create others with each day's hours and the working day used to turn labor hours into days. Exceptions are single days or ranges, working or not, and can repeat every year. “National holidays” adds those of Paraguay, Spain or Mexico for this year and the next two at once, Easter included.

Scheduling
- In the budget's “Gantt” view press “Schedule”.
- Choose “From the start” or “From the finish”: from the finish, everything goes as late as possible to finish on the given day.
- Choose the working calendar and, if you want, the people in the crew.
- Leave “Reschedule automatically…” ticked so dates are redone when links, durations, quantities or the calendar change.

The critical path
With early and late dates, every item has its total slack (how much it can slip without moving the project finish) and its free slack (how much it can slip without moving the next ones). Critical items are red on the Gantt and in the chart's PDF, and the “Critical path” filter shows only those. A deadline that is missed gives negative slack and puts the item on the critical path. When scheduling you choose the slack below which a task counts as critical.

Moving and stretching bars
As in MS Project, moving a bar fixes it with “Start no earlier than” that date, and stretching it changes its duration. Constraints can also be chosen on the item's form (start or finish no earlier or no later than, must start or finish on), next to the deadline.

Baseline: what was planned
When the schedule is approved, “Save baseline…” in the Gantt's “Baseline” menu saves the dates, duration, work (labor hours) and cost of every chapter and item. There are eleven, as in MS Project: the “Baseline” and 1 to 10. You can save the whole budget or only what is selected in the tree, and chapters are summarized again from their items. The same menu chooses which one to compare with.

Actuals and the status date
Progress comes from the daily reports: an item's first report with a quantity is its actual start and, once it is all done, the last one is its actual finish. If you prefer, type “Actual start”, “Actual finish” and “% complete” on the item's form, which take precedence over the reports. What is done no longer moves when rescheduling: if an item finishes early the next ones come forward; if it started late, they are pushed back.
- “Update project…” takes what was scheduled up to a date as done, by the share of days passed or only 0 % or 100 %.
- The other option, “Reschedule uncompleted work…”, moves what is left after the status date, except items with “Must start on” or “Must finish on”.
The tracking Gantt
The “Tracking” chip puts the baseline bar in grey under each bar, fills in the part already done and draws the status date and the progress line, which goes through each item's progress: a peak to the left is a delay and to the right, ahead of schedule. The columns change to “% compl.”, “Planned start”, “Planned end” and “Finish var.”, the variance in working days. “Project statistics” sums up current, baseline, actual and remaining start, finish, duration, work and cost.

Resources: who works each day
The Gantt's “Resources and costs” button opens “Resource usage”: the hours of each trade and each machine per week or per day. They come from each item's hours per unit (the productivity of its labor and equipment) spread over its working days. Each resource has its capacity, how many people or machines are available at once, and what goes over is red, with a histogram of the selected resource.
- “Level…” delays items that do not fit, by start date, priority and slack, as MS Project does.
- With “Level only within available slack”, the project finish does not move even if some over-allocation remains.
- Started items and those with priority 1000 do not move. “Clear leveling” undoes it, and the Gantt's “Leveling” chip shows the dates from before.

Cash flow and S-curve
The “Cash flow” tab spreads each item's cost over months or weeks, at the start, prorated or at the end, and draws a four-line S-curve: what is scheduled, the baseline, what is certified and what is spent on purchase invoices of the budget's analytic account. The table with each period goes underneath. If a material or a trade gets more expensive from a date, record it on the resource and the cash flow takes it into account without changing the budget amount.

Reports and MS Project
“Print” › “Schedule reports” produces the project summary, top-level tasks, critical tasks, milestones, slipping tasks, tasks starting soon, cash flow and weekly resource usage as PDF.
To work with people who use MS Project, Export › “MS Project (XML)” saves the schedule in MS Project's XML, which ProjectLibre and Primavera also open, with tasks, links, constraints, progress, baseline, calendar and work resources. “Import” accepts that same XML: summary tasks become chapters, the rest items, and the project ends up scheduled.

Split tasks
If an item stops and then resumes, type in “Splits” how many days are worked and how many are paused: 3+2 means three days of work and two of pause. The Gantt draws the gap with dots, the work duration does not change, and resource usage and cash flow do not count those days.

Estimated duration and cost per use
A duration that is not clear yet is written with a question mark, “5?”, as in MS Project: the form and the Gantt show it that way until it is confirmed, and it travels in the XML.
Each resource can have a cost per use: a fixed amount for each item that uses it, such as moving a machine to site. It counts in the cash flow when the item starts, without changing the budget amount.
In the Project app, each blocking task has its type: finish-to-start, start-to-start, finish-to-finish or start-to-finish, and the Gantt draws the arrow for each one.

What it does not do yet
- Reports come out as PDF; the printed “Resource usage” shows up to 12 weeks.
- Splits, material and cost resources and more than one baseline are not read from or written to MS Project XML.
- Overtime rates: the app does not record overtime in the schedule or in the daily reports.
Frequently asked questions
Can I schedule without links?
Yes. If you type no predecessors, items are chained one after another in tree order, which is what scheduling by performance did.
What about holidays?
Normal items do not work on the calendar's non-working days; consecutive-day items (3dt) keep counting.
Does the AI assistant know about links?
Yes. It can create and remove links and mark milestones, and it uses the budget's calendar when comparing crews.