v1.1.43

Construction scheduling like MS Project: links, calendars and critical path

What's new in ERPSqlite 1.1.43

  • Links between chapters and items with the four MS Project types (finish-to-start, start-to-start, finish-to-finish and start-to-finish) and lead or lag in days or %. Type them in “Predecessors” with the code (3FS-2d, 4SS+25%) or draw them on the Gantt by dragging the dot at the end of a bar onto another.
  • Working calendars: “Standard”, “Night shift” and “24 hours” built in, with each day's hours, the working day and exceptions (holidays, shutdowns or extra working days). “National holidays” adds those of Paraguay, Spain or Mexico for this year and the next two.
  • Critical path: every item has its total and free slack and its latest start. Critical ones are red on the Gantt and in the PDF, and the “Critical path” filter shows only those. When scheduling you choose the slack below which a task is critical.
  • Written duration (5, 2 wk, 16h) or consecutive days (3dt, for curing and drying that do not stop on holidays), milestones with their diamond, constraints such as “Start no earlier than” or “Must finish on”, and a deadline.
  • The “Schedule” button opens a new dialog: from the start or from the finish of the project (everything as late as possible to finish that day), calendar, people in the crew and whether it reschedules automatically when links, durations, quantities or the calendar change.
  • The Gantt has columns for duration, start, finish, predecessors and slack, and shades the calendar's non-working days. Moving a bar fixes it with “Start no earlier than” and stretching it changes its duration, as in MS Project.
  • The budget AI assistant understands links and milestones, and uses the calendar when comparing crews.